The wellhead process platform includes a 30 man accommodation unit and deck space to support the well clean-up following drill rig departure. The topsides has a lift weight of 1750 tonnes and the jacket is around 1800 tonnes with 1000 tonnes of piles.

SLP Project Manager, Paul Thomson said; “It is notable that the assembly of the structural steel commenced on the 2nd February this year; to achieve sail away by September 17th is a significant achievement. Many thanks and congratulations to all involved.”