Enterprise will construct an additional 300 million cubic feet per day (MMcf/d) train at its Yoakum cryogenic natural gas processing facility along with the execution of new gathering and processing agreements in Lavaca County, Texas.

The Yoakum natural gas processing facility currently has 600 MMcf/d of capacity under construction, expected to begin service during the second quarter of 2012.

Upon operational, the plant will have a total capacity of 900 Mmcf/d expected in the first quarter of 2013.

In addition, the firm has plans to construct 62 miles of 24-inch diameter and 30-inch diameter pipeline loops and increase horsepower compression to gather, and transport an additional 300 MMcf/d of rich Eagle Ford Shale gas.

The expansion is expected to begin service in the first quarter of 2013.