The Alaska Pipeline Project has filed its plan with the US Federal Energy Regulatory Commission (FERC) to obtain approval to conduct a natural gas pipeline open season to develop Alaska's natural gas resources.

The project is a joint effort between TransCanada and Exxon Mobil to develop a natural gas pipeline under the Alaska Gasline Inducement Act (AGIA).

Hal Kvisle, president and CEO of TransCanada, said: “The open season plan filing is an important step in the development of Alaska natural gas resources and we have worked diligently to advance the project.

“This significant milestone demonstrates that we are meeting the AGIA commitments on-schedule and in-line with the required process, effectively aligning the interests of the state of Alaska, the project, shippers and other interested parties.”

If FERC approves the plan, the Alaska Pipeline Project will finalize its open season offering and provide it to potential shippers at the end of April for their assessment during the 90-day period through July 2010.

During the open season, the Alaska Pipeline Project will provide information about its terms and conditions to potential natural gas shippers, allowing them to assess their interest in making long-term commitments to reserve capacity on the pipeline.

The open season process initiated with FERC applies to the US portion of the project. A separate but coordinated open season for the Canadian portion of the project will be conducted concurrently with the US open season.

Two options will be submitted for shipper assessment in the Alaska Pipeline Project open season. The first option is a pipeline from Alaska’s North Slope to Alberta, Canada, a distance of approximately 1,700 miles, where the gas can be delivered on existing pipeline systems serving North American markets.

The second option would transport natural gas from the North Slope to Valdez, Alaska, a distance of approximately 800 miles, where it would be converted to liquefied natural gas in a facility to be built by others and then delivered by ship to North American and international markets.

Both options are expected to provide opportunities for Alaska communities to acquire natural gas from the pipeline from a number of off-take connections.

Components of both options include a gas treatment plant (GTP) and Point Thomson natural gas transmission pipeline. The GTP would be built next to the North Slope’s Prudhoe Bay facilities to treat the gas so it can be shipped on the pipeline. An approximately 58 mile pipeline would connect the natural gas supplies of the Point Thomson field to the plant and pipeline.

The results of the open season will determine the preferred development option. Updated cost estimates for the project are in the range of $32bn to $41bn for the North Slope to Alberta option, and $20bn to $26bn for the Valdez option. Both options have an expected in-service date of 2020 and would provide either 4.5 billion cubic feet of natural gas per day under the Alberta option or three billion cubic feet per day under the Valdez option.