Construction of a fuse plug spillway at Copeton Dam in Australia is one of several safety upgrades being undertaken. By Nava Jeyachandran and Jane Urquhart.

main

Copeton Dam

Copeton Dam is a 113m high, zoned, clay core, rockfill embankment dam, located on the Gwydir River in northern New South Wales (NSW), Australia. The dam is owned and operated by State Water Corporation and is a major piece of infrastructure for NSW. It is a very popular location for recreation, with more than 100,000 visitors each year to the Copeton Waters State Park (CWSP).

Constructed in three stages between 1968 and 1976, the dam impounds a maximum storage of 1,364,000 ML. The reservoir plays a major role in sustainable water management through its flood mitigation, environmental releases and river flows. Copeton Dam supplies water to meet the town water, stock and irrigation demands of Moree, Inverell and Bingara.

A separate gated spillway consisting of nine radial gates and a concrete chute is located 500m from the dam on the right abutment. This has the capacity to release 1,280,000ML/day.

"Without dam safety upgrade works there was a risk of dam failure in extreme flood events."

Dam safety reviews have identified Copeton Dam as an ‘Extreme’ flood consequence category (FCC) dam, which does not meet the statutory requirements of the NSW Dams Safety Committee (DSC) safety standard requirements and the Australian National Committee on Large Dams (ANCOLD) guidelines. Under both ANCOLD guidelines and NSW DSC requirements, extreme consequence dams are required to be able to safely pass the probable maximum flood (PMF) with the reservoir at full supply level (FSL). Without dam safety upgrade works there was a risk of dam failure in extreme flood events. This risk results from the inability of the existing gated spillway to release a sufficient volume of water, potentially causing the embankment to overtop and leading to a possible failure of the dam wall. The failure of Copeton Dam wall would have catastrophic downstream impacts; economically, environmentally and socially.

Two stage safety upgrade

To achieve PMF compliance, State Water embarked on a major upgrade of the dam to ensure that it can handle extreme floods. This involves two stages of construction:

  • Stage 1: Construction of a fuse plug at Diamond Bay (completed in 2013).
  • Stage 2: Raising the dam wall, with spillway gate modifications (future works).

Stage 1 of the safety upgrade involved the construction of an auxiliary fuse plug spillway in the Diamond Bay area of the dam storage, approximately 1km from the left abutment. The new spillway is 250m wide, 12m deep and divided by concrete divider walls into four fuse plug sections. At full supply level, the fuse plugs will store up to 6.5m of water against them. Should the existing spillway capacity be exceeded the new fuse plugs would activate. Each bay of the spillway is designed to release sequentially to pass extreme flood events. The first of the four bays will be designed to trigger at a 1 in 2000 annual exceedence probability (AEP).

Stage 1 works reduced the risk of the dam over-topping by increasing the discharge capacity of Copeton Dam’s spillway from 48% of the PMF to 86%. The dam’s spillway capacity increased from an AEP flood of 1:7200 to accommodate an AEP flood of 1:190,000.

The Stage 2 works (future works) involves raising the dam crest by 1.65m, along with modifications to the existing spillway gates to accommodate a PMF. The Stage 2 works will be subject to a portfolio risk assessment.

Stage 1 works at Copeton Dam

Stage 1 of the upgrade commenced in April 2011 and was completed in March 2013. In broad terms, it included the following:

  • Construction of a temporary public access road upstream of the proposed auxiliary spillway channel on top of the upstream cofferdam.
  • Construction of an upstream cofferdam to protect the works and to accommodate the temporary public road.
  • Removal of the cofferdam on completion of the fuse plug auxiliary spillway construction.
  • Bulk excavation (more than 1.2Mm3 of predominantly granite material excavated from blasting) for a fuse plug auxiliary spillway channel, including stabilisation of the spillway channel cut slopes with rock bolting and shotcrete. An Endangered Ecological Community (EEC) adjacent to and downhill of the spillway excavation was well protected during the construction process.
  • Construction of a single row grout curtain along the alignment of the fuse plug core.
  • Construction of a four-bay fuse plug concrete structure including floor slabs anchored to the rock, cut-offs, divider walls, and abutment side walls.
  • Construction of fuse plug embankments within the bays of the fuse plug concrete structure.
  • Permanent re-construction of Fossickers Way Road along the existing road alignment and across the auxiliary spillway channel downstream of the fuse plug structure.
  • Installation of security fencing, floating safety barrier, road barriers, and signage.
  • Provision of permanent site drainage, site cleanup, landscaping, revegetation and disestablishment of all temporary facilities including the temporary road, and removal of construction debris on completion.

The engineered cofferdam was constructed to provide a dry area for construction regardless of the water level in the dam. This meant the project could continue without any increased risks to the downstream communities and that the construction activities and normal dam functions weren’t affected despite the dam’s water level rising from 50% to 100% of capacity (17.8m of water) during construction.

To make way for the new spillway, comprehensive consultation contributed to successfully relocating CWSP infrastructure facilities, power lines, water mains, telephone lines and other items prior to construction of the fuse plug spillway. New park facilities were also constructed including a new administration building, manager’s residence, water playground, picnic tables, road infrastructure and other facilities. Careful planning and consultation meant access to the park was operational throughout the works.

"The project was completed five months ahead of schedule, 23% under budget with excellent quality and environmental outcomes."

Blasting work was carried out within close proximity to the operational recreation park. Monitoring of all blasts for noise, vibration and dust were undertaken for each of the 40 blasts. The results indicate that all blasts complied with the requirements of the specification and did not exceed the acceptable limits. There were no reports of flying rock from the blasts travelling any further than 100m from the front face of the blasts.

Safety was a major consideration during the project and no lost time injuries were recorded over some 98,000 hours of work. Only 13 minor incidents occurred and were reviewed and any necessary actions taken to prevent recurring.
A comprehensive communication and consultation strategy was also implemented during the project. More than 130 positive media articles were recorded in local, state and national media during the works.

The project was completed five months ahead of schedule, 23% under budget with excellent quality and environmental outcomes. Indeed the Copeton Dam Safety Upgrade Project won a Highly Commended Award in the Project Management category of the 2013 Engineers Australia Sydney Division Engineering Excellence Awards.


About the authors

Nava Jeyachandran is Project Manager (Copeton Dam Safety Upgrade), Major Projects, State Water Corporation
Jane Urquhart, Senior Communication Officer – Major Projects, State Water Corporation