The Assa North-Ohaji South project (ANOH) is one of the largest greenfield gas condensate development projects being undertaken in Nigeria.

The project involves the development of the Ohaji South gas and condensate field located within the license block OML 53 and the Assa North field in license block OML 21.

The two fields are together expected to produce 600 million standard cubic feet per day (Mscfd) of gas, equivalent to approximately 2.4GW of electricity. The generated electricity is sufficient to supply for approximately 2.4 million homes.

ANOH Gas Processing Company (AGPC), incorporated in 2017, is responsible for the project development and operation and maintenance. Seplat holds 50% stake in AGPC, while Nigerian Gas Company (NGC), a wholly owned subsidiary of NigerianNational Petroleum Corporation (NNPC), holds the remaining stake.

Final investment decision on the project was made in December 2018, with commissioning planned to be completed by the first quarter of 2020. The field is expected to produce between three and 3.4 billion standard cubic feet of gas per day by 2020.

Ownership of license blocks OML 53 and 21

Shell Petroleum Development Company of Nigeria Limited (SPDC) holds 30% stake and is also the operator of the JV that owns the license OML 21. Other partners in the JV include Nigerian National Petroleum Corporation (NNPC, 55%), Total Exploration and Production Nigeria (10%), and Nigerian Agip Oil Company (5%).

NNPC holds 60% stake in the OML 53 license, while the remaining stake is owned by Seplat. The two companies will hold an upstream unit interest in ANOH of 30% and 20%, respectively.

Assa North-Ohaji South project location and background

ANOH is one of the seven critical gas projects initiated by the Ministry of Petroleum and the Nigerian National Petroleum Corporation (NNPC) to meet the increasing gas demand in Nigeria.

The project extends in 719.84km2 in the Imo state and is located approximately 25km from Owerri and 75km from Port Harcourt.

Shell initiated the preliminary project development and conducted environmental impact assessment (EIA) studies in 2006 and front-end engineering and design (FEED) in April 2007.

The final cumulative EIA report was submitted to the  Federal Ministry of Environment of Nigeriain September 2015 and the same was approved in February 2016.

Assa North-Ohaji South project reserves

The Assa North and Ohaji Southfields are expected to contain reserves of 4.3 trillion cubic feet (Tcf) of gas in addition to 215 million barrels (Mmbbls) of condensate.

Assa North-Ohaji South project details

The Assa North field hosts hydrocarbon reserves in the north-eastern segment of OML 21, which extend into the Southern segment of OML 53.

The project is being developed in two phases, with the first phase involving the construction of two main reservoirs H1000 and H4000. The second phase involves the depletion compression, with potential to further develop other lower-ranking reservoirs.

Four development wells will be constructed in the H1000 reservoir, while twowells will be constructed in the H4000 reservoir. All the wells will be pre-drilled from a single drilling centre and forwarded to three inlet manifolds of PTF through individual flowlines.

Gas will be processed through dehydration and hydrocarbon dew pointing processes to meet the sales specifications, while the liquids will be processed by condensate stabilisation and dehydration methods.

The project will be connected to large-scale gas reserves to Nigeria’s main demand centres through the Oben hub owned by Seplat. The produced gas will be treated at the processing facility owned by SPDC JV and then forwarded through the Obiafu-Obrikom-Oben pipeline network.

Gas treatment

Gas will be treated at the primary treatment facility (PTF) to be located between the existing Assa North-1 surface drilling centre and the Assa flow station. The facility is estimated to have a capacity of 600Mmscf/d gas and 45,000bbl/d of condensate.

The PTF will comprise two 300Mmscfd gas dehydration facilities, 15 wellheads, associated flowlines for H1 and H4 wells, NAG inlet facilities for H1 and H4 wells, and other facilities. The stabilised liquids are proposed to be stored at the four 100,000bbl tanks.

The processing plant will comprise two Thompson trains with a turndown capacity of 50%. It will also feature a 20,000bbl/d two-train condensate plant, which is capable of recovering 1,200bbl/d of LPG.

Of the total gas production, 300Mmscfd will be processed at the new gas processing plant owned by the SPDC JV, while the remaining gas will be processed at the proposed processing plant by SEPLAT Petroleum.

The processed gas will be transported to the Escravos-Lagos Pipeline System (ELPS) and West African Gas Pipeline (WAGP) through a 26km-long spur line connecting to the OB3 pipeline. The produced LPG will be trucked directly to Owerri, while the condensate will be exported to either Shell Bonny and or ENI’s Brass River terminal.

Financing of Assa North-Ohaji South project

The phase one development of ANOH midstream is expected to cost $700m, of which the JV of Seplat and NGC will fund $420m. AGPC proposes to raise $280m in debt comprising senior tranche and vendor financing.

Infrastructure facilities at ANOH

The existing infrastructure at the Assa North field includes a pipeline manifold and a mothballed flow station.

Major infrastructure facilities will include a field logistic base (FLB), pipelines, flare gas system, seven 500kVA low-voltage emergency diesel generators, tri-ethylene glycol storage, distribution and regeneration units, and six flow lines.

Power supply for the project will be provided by two 1.6MVA onsite diesel generators, while potable water is proposed to be sourced from the onsite stormwater storage facility.